Dubai, UAE  ·  Freelance PT · RC · Steel design

Freelance design, to the millimetre.

A Dubai Municipality licensed structural engineer, engaged directly. Post-tensioned, reinforced concrete and steel design to the authority’s submission format — plus the software we built to do it faster.

Licence 01
DM Unlimited Design
Licence 02
DM Post-Tension Design
Engagement
Fixed fee · Per floor · Day rate
Columns Drag to orbit
0
Years in PT & RC
0
Dubai Municipality licences
0
Countries delivered
0
In-house design tools
0
Design standards in use
S-101 Freelance design

Freelance PT & RC design, direct from the engineer.

Engage a Dubai Municipality licensed structural engineer directly. No account layer, no junior redraw, no waiting on someone else's resourcing. You talk to the person who runs the model and signs the calculation.

01 — Direct line

Your question reaches the engineer

Queries go to the person who built the model and come back the same working day. Nothing is relayed through a project manager, and nothing is lost on the way.

02 — Licensed to submit

Issued ready for the authority

Dubai Municipality Unlimited Design and Post-Tension Design licences. What you receive is a submission package in the authority's format and your consultant's specification — not advice you still have to package.

03 — Priced per scope

You know the number first

A fixed fee against a defined package, a rate per floor, or a day rate for overflow work. Agreed before anything starts, and it does not move unless the scope does.

01 / Fixed fee

Full design package

Scheme through to authority submission for a defined building — analysis, calculations, drawings, schedules and the submission set, delivered as one coordinated package.

Best for — a whole project, start to finish
02 / Per floor

Post-tensioning by the slab

Priced per typical floor or by slab area. Tendon layout, drape and chair profiles, punching design and the detailing set for each level, issued floor by floor to suit the pour programme.

Best for — towers with repeating floors
03 / Overflow

Design office capacity

Slot in behind your own team when the office is loaded. We work in your templates, your title block and your CAD standard, under your review and your professional cover.

Best for — consultancies at capacity
04 / Day rate

Review, RFI & comment response

Independent checking, authority and consultant comment responses, RFI cover and method statement review — charged by the day or half-day against a defined, short scope.

Best for — a bounded piece of work
Every package includes
  • Design calculation report — bound and clause referenced
  • Analysis model handed over: RAM Concept, ETABS or SAFE
  • Drawings in your CAD standard, DWG and PDF
Post-tensioning adds
  • Tendon layout and drape profile drawings
  • Chair profile schedule the steel fixer can work from
  • Stressing schedule — elongation and gauge pressure
On request
  • Authority submission set and resubmission
  • Compliance statement answering review comments
  • Site technical support through construction
S-102 The practice

A design office built around post-tensioned concrete.

Most consultancies treat post-tensioning as a specialist item to be subcontracted. We treat it as the starting point of the structural scheme — because that is where the thickness, the programme and the cost are actually decided.

Iron Axis is led by Mohamed Shahid PK, a structural engineer with more than fourteen years in post-tensioned and reinforced concrete design, holding both Dubai Municipality Unlimited Design and Post-Tension Design licences.

We work the whole way down the chain: scheme and slab optimisation, full analysis and design in concrete and steel, detailing and drawing production, authority submission, and technical support once the job is on site — reviewing method statements, answering RFIs, and checking specialist submittals for post-tensioning, façade and steelwork.

The practice works alongside Smart Slab Prestressed Concrete Contracting, a Dubai post-tensioning specialist contractor. That gives our design decisions a rare feedback loop — we see how the tendons are actually laid, stressed and grouted, and it shows in the buildability of what we detail.

Base
Dubai, United Arab Emirates
Reach
UAE · Kingdom of Saudi Arabia · Qatar · India
Systems
Unbonded monostrand & bonded multistrand PT, RC frames and flat slabs, transfer structures, structural steelwork
Analysis
RAM Concept · ETABS · SAFE · STAAD.Pro
Production
AutoCAD · Revit · AutoLISP · Python automation
Approach
Conservative design, SI units, fully checked and traceable calculations
Compliance
Documented to the governing authority’s submission format and the lead consultant’s specification
S-201 Services

What we are asked to do.

Three core disciplines — post-tensioned concrete, reinforced concrete and structural steel — plus the specialist scopes around them. Every package is designed, checked and documented to the governing authority's requirements and the lead consultant's specification, so it goes in once.

01 / PT

Post-tensioned slab design

Banded and distributed layouts, drape profiling, prestress and thickness optimisation, transfer and service checks, deflection and crack control, hyperstatic effects.

ACI 318-19PTI DC80EC2
02 / RC

Reinforced concrete design

Full building design — frames, flat slabs, beams, columns, shear walls and cores — with lateral analysis, drift checks and seismic detailing to the governing code.

ACI 318-19IS 456BS 8110
03 / STL

Structural steel design

Steelwork from member sizing to connection design — moment and shear connections, base plates, bracing, composite decks, staircases, canopies and façade support steel — plus independent review of PEB and specialist steel submittals.

AISC 360EN 1993 · EC3BS 5950AWS D1.1
04 / FDN

Foundations & geotechnical interface

Rafts, piled rafts, isolated and combined footings, under-reamed piles, crane and plant foundations. Settlement, bearing and soil–structure interaction reviewed against the GI report.

IS 2911IS 6403ACI 318
05 / PSD

Punching shear & detailing

Critical perimeter checks, stud-rail and stirrup schedules, shear caps and drop panels, with detailing output produced directly from the analysis results — not redrawn by hand.

ACI 318-19 §22.6EC2
06 / REV

Peer review & value engineering

Independent checking of a third-party design, slab thickness and prestress optimisation, and structured compliance statements answering authority and consultant design-review comments point by point.

Independent checkAuthority commentsVE
07 / STR

Strengthening & forensic assessment

Assessment of overloaded, damaged or altered structures, residual capacity checks, and CFRP flexural and shear strengthening design with full bond and detailing checks.

ACI 440.2R-17ACI 562
08 / SITE

Site technical support

Method statement and temporary works review, RFI response, submittal review for post-tensioning, façade and steel structure packages, and coordination with architects, MEP and the main contractor.

BS 5975EN 12812
S-301 Post-tensioning

The drape is the design.

Get the tendon profile right and the slab gets thinner, the deflections disappear and the programme shortens. Get it wrong and no amount of rebar recovers it.

DRAPE 165 SPAN 8.0 m 250 LOW POINT AT 0.5L A — ELEVATION B — PLAN BANDED — OVER COLUMN LINES DISTRIBUTED A A
Fig. 3.1 — Banded / distributed layout. Continuous unbonded tendon, reverse curvature over supports.

Every post-tensioned slab we design is checked at transfer and in service, for flexure, punching, deflection and crack width, with the hyperstatic effects carried properly through to the reinforced concrete design. Nothing is left to a rule of thumb.

We work in both unbonded monostrand — the system that dominates Middle East practice — and bonded multistrand, and we produce the tendon layouts, chair profiles, stressing schedules and elongation records that the specialist contractor actually needs on site.

P/A
Precompression checked span by span
Δ
Long-term deflection with creep & shrinkage
wk
Crack width to the governing exposure class
S-302 Tips & tricks

Nine things that decide a PT slab.

The working rules we apply at scheme stage, before a single tendon is drawn. They set the starting point — the design is still whatever the calculation says.

A — Sizing

  1. 01

    Set the depth before the load

    Span/depth drives everything downstream. For interior spans of an unbonded flat slab, L/d ≈ 40–45 works with light superimposed load; come down to 36–38 where deflection-sensitive partitions, long cantilevers or heavy finishes govern. Fix the thickness first — prestress and rebar are the cheap variables.

    L/d 40–45
  2. 02

    Precompression is the real dial

    ACI 318-19 sets a minimum average effective prestress of 0.86 MPa on the gross section for two-way slabs. The useful working range is roughly 1.0–2.0 MPa. Push past about 2.5 MPa and you buy restraint cracking and axial shortening, not capacity.

    P/A 1.0–2.0 MPa
  3. 03

    Balance the sustained load, not the total

    Balancing much above 85% of dead load tends to hog the slab and leave long-term upward camber. Much below 55% and you have paid for a PT system that behaves like a conventional slab. Aim between the two and let the unbalanced load run the deflection check.

    60–80% of DL

B — Analysis

  1. 04

    Punching governs earlier than flexure

    Run the punching check on the first thickness iteration, not the last. The vertical component of the tendon force only helps where the tendons actually cross the critical section — and stud rails retro-fitted after the layout is frozen will force the tendons to move.

    Check at iteration 1
  2. 05

    Check transfer, not just service

    At stressing the concrete is young — f′ci is often only 22–28 MPa at three to five days — and there is almost no superimposed load holding the slab down. Top-fibre tension over supports at transfer catches more otherwise-sound designs than the service check does.

    f′ci at 3–5 days
  3. 06

    Model the restraint

    Stiff cores and shear walls absorb the prestress you assumed went into the slab. On long floor plates put pour strips in at roughly 40–50 m centres and leave them open long enough for the early shortening to happen. Assume a free slab and you will find the cracks on site.

    Pour strips 40–50 m

C — Detailing & site

  1. 07

    The drape you draw must be buildable

    Usable drape is what survives top and bottom cover, the sheathing and the bars crossing it — for a 250 mm slab that is around 165 mm, not 200. Check it against the chair heights the contractor can actually buy before it goes on the drawing.

    250 slab → 165 drape
  2. 08

    Two tendons through every column core

    The structural-integrity rules require at least two tendons in each direction to pass within the column core. It is the detail most often lost when a layout is shifted around a late opening — and it is the one that matters if a column is ever lost.

    2 tendons min., each way
  3. 09

    Issue the stressing schedule with the layout

    Theoretical elongation, gauge pressure, stressing sequence and the acceptance band — typically ±7% — belong on the drawing set, not in an email three weeks later. It is the difference between a clean QC record and a site query per tendon.

    Elongation ±7%

Figures quoted are scheme-stage rules of thumb for unbonded monostrand flat slabs to ACI 318-19, offered in good faith and not a substitute for project-specific design. Ask us and we will run the numbers on your grid.

S-303 Estimator

Size the slab before you call.

Move the sliders. This runs the same scheme-stage rule set as the nine above — span/depth, load balancing and a minimum precompression floor — so you can see in ten seconds whether post-tensioning is worth the conversation.

System
8.00 m
2.00 kPa
2.00 kPa
Deflection sensitivity
Bay condition
200 mm slab PT flat slab
Span / depth
1 : 42
Self weight
5.0kPa
Service load
9.0kPa
Precompression
1.35MPa
Strands 15.7 mm
1.6per m
Untensioned rebar
11kg/m2
Thickness comparison
PT 200 mm
RC 290 mm
Post-tensioning saves 31% of the concrete on this grid

Scheme-stage indication for an unbonded monostrand flat slab on a regular grid, load balanced at 70% of sustained load with a 0.86 MPa precompression floor. Not a design. Punching, transfer, restraint and deflection all still have to be checked properly.

S-401 Iron Axis tools

Automation, built in-house.

Over twenty in-house applications sit behind the practice — reading model exports, running the code checks and writing the drawings. They remove the transcription step, which is where errors actually come from.

01

DXF → ETABS / RAM Concept

Reads AutoCAD geometry straight from the architectural DXF and builds the analysis model — slabs, beams, columns, walls and openings — without redrawing a line.

02

Tendon layout & chair profiles

Generates tendon runs, drape profiles and chair heights from the slab geometry, then writes them back into the drawing as real CAD entities.

03

Punching shear suite

Takes the RAM Concept punching export, runs the ACI 318-19 check and produces the stud-rail schedule and the detailing callouts on the plan.

04

Thickness & prestress optimiser

Sweeps slab thickness and prestress against deflection, punching and stress limits, driven directly from the live ETABS model through the API.

05

Rebar detailing engine

Converts required-reinforcement contours into practical bar marks, laps and schedules — drawn on the plan, not left as a table for someone else to interpret.

06

Beam & slab design generator

Full-span RC beam and slab design to ACI 318-19 or IS 456:2000, output as a dimensioned drawing with the calculation behind it.

07

Foundation layout generator

Preliminary isolated and combined footing layouts straight from the column load schedule, sized against the allowable bearing pressure.

08

Stressing & grouting records

Gauge-pressure calculation, measured elongation checked against theoretical, and the QC record set the authority asks to see.

09

Compliance statement builder

Turns an authority or consultant review-comment schedule into a structured, clause-referenced response document ready for resubmission.

Every tool runs offline — single-file HTML, or a Windows executable. Nothing leaves the office. Built for our own delivery first; where one is useful to a client's design office, we license or adapt it.

S-402 Software

Buy the tools we design with.

The same applications that run behind our own delivery, licensed for your design office. Everything runs offline — a Windows executable or a single HTML file — so nothing about your project leaves your machine.

Perpetual licence  ·  one year of updates  ·  order and pay over WhatsApp

Card payment linkBank transferCash Orders are confirmed on WhatsApp — we send a payment link or bank details, then the licence key and download by email. No card details are entered on this page.  ·  WhatsApp +971 52 118 2569
S-403 Learn

Watch it work.

Design walkthroughs and software demonstrations from the drawing board — the reasoning behind the decisions, not just the button presses.

S-501 Delivery

How a job runs.

A fixed sequence, so you always know which stage the design is at and what is needed from you next.

STAGE 01

Brief & constraints

Architectural set, GI report, loading, authority requirements and programme.

STAGE 02

Scheme & optimisation

Framing options, slab type and thickness, prestress level, comparative cost.

STAGE 03

Analysis & design

Full model, gravity and lateral, all code checks at transfer and service.

STAGE 04

Detailing & drawings

Tendon layouts, rebar, sections and schedules issued as a coordinated set.

STAGE 05

Authority submission

Calculation report, submission set, and structured replies to review comments.

STAGE 06

Site support

RFIs, method statement review, stressing records and as-built resolution.

S-601 Sectors

Where the work sits.

Projects delivered across the UAE, Saudi Arabia, Qatar and India — typically where a long span, a thin slab or a difficult transfer is driving the structure.

Residential

High-rise & mixed-use towers

PT flat slabs over podium and typical floors, transfer structures, core-and-outrigger layouts.

Commercial

Retail podiums & offices

Long-span column grids, heavy point loads, coordination with MEP service zones.

Substructure

Basements & podium decks

Water-retaining detailing, crack control, pour strips and construction joint strategy.

Industrial

Steel structures & plant

Portal frames and PEB review, mezzanines and platforms, tower crane bases, machine foundations and heavy industrial slabs.

Remedial

Strengthening & assessment

Overload and damage assessment, CFRP strengthening, change-of-use capacity checks.

Low-rise

Villas & G+ developments

Conventional RC design with pile or pad foundations, delivered to local authority format.

S-701 Contact

Send us the architectural set.

Give us the plans, the loading and the programme, and we will come back with a framing option, an indicative slab thickness and a fee.

Opens in your mail client — no data is stored by this page.

Office
Dubai, United Arab Emirates
Attention
Mohamed Shahid PK — Structural Engineer
Hours
Sunday – Thursday, 09:00 – 18:00 GST

⟨ office address is a placeholder — replace before publishing ⟩

For post-tensioning supply and installation, we work with Smart Slab Prestressed Concrete Contracting — ask us and we will route the enquiry.

0 item(s)  ·  total AED 0